Rural housing reaches only 66% target.
States are delaying the allotment of land for landless beneficiaries, says Centre.
With two and a half months to go for the end of this financial year, the Pradhan Mantri Awas Yojana (Grameen) scheme to provide housing for the rural poor has achieved only 66% of its target to complete one crore houses.
The Ministry of Rural Development still hopes to advance further towards the goal by the deadline of March-end, given that about 15 lakh homes have reached the late stages of construction with roofs ready to be added. Another 11 lakh homes have reached the lintel level, and may be completed in the next few months even if they do not meet the March 31 deadline. The scheme has been successful in reducing the average time of construction from 314 days to 114 days, according to an official statement.
However, there has been little headway made with regard to one bloc of beneficiaries: the landless, who do not possess the land on which to construct the PMAY homes they are entitled to.
In a letter to States dated January 4, the Ministry pointed out that only 12% of the 4.72 lakh identified landless beneficiaries had been provided land for house construction.
Laggard States
According to data provided in the letter, some of the most laggard States as of July 2018 were Maharashtra, which had provided land for only 890 of 1.39 lakh landless beneficiaries and Assam, which had provided land for 574 of 48,283 landless beneficiaries. In Bihar, only 55 out of 5,348 beneficiaries had been allotted land. West Bengal had not allotted land for even a single one of its 34,884 landless beneficiaries. “There are about 2.4 lakh left [to be sanctioned] in Bihar and about 30,000 each in Andhra Pradesh and Tamil Nadu,” said a senior official of the Ministry. (Source: The Hindu)